April 2006 Project Kick-off Meeting with City Staff
Spring-Summer 2006 Background Data Research, Study and Analysis
Summer 2006 Public Workshop #1: Visioning, Opportunities & Constraints
Summer 2006 Public Workshop #2: Visioning, Opportunities & Constraints II
Late Summer 2006 Preparation of Land Use Alternatives
Early Fall 2006 Public Workshop #3: Land Use Alternatives Design Charrette
Fall 2006 Preparation of Preferred Land Use Alternative
Winter 2007 Public Workshop #4: Walking Tour
Winter 2007-Spring 2009 Refinement of Preferred Land Use Alternative
Summer 2009-Fall 2011 Preparation of Public Review Draft Specific Plan
Summer 2009-Fall 2011 Preparation of Environmental Impact Report
December 2011 Release of Specific Plan & Draft EIR for Review
Spring 2012 Planning Commission and City Council Hearings
Spring 2012 Preparation of Final Specific Plan